Monica, Which set of dates are you implementing your plan against? If you are implementing against the negotiated rebaselined dates then I would create the initial plan using the planned dates (predecessors, durations, the works!), snap a baseline, and then change the planned dates (by modifying durations & predecessor lead/lag times) based on the negotiation. Then it is real easy to create a view or report that has the baseline dates (your original plan), current planned dates (negotiated dates), and actual dates next to each other to compare and even do some calculations if you want. Please let me know if you have any questions, David
DAVID A. TAYLOR Founder & Managing Consultant