Any way to connect due dates between a request and a task?
Hi
I've become a real fan of cross-project predecessors and have been using them like this:
- Master project is the Campaign - which has 1 task for each of the assets, materials or whatever that is needed to launch the campaign. It acts more like a checklist and a way to show all the various things we need for the campaign
- Other projects are those that require a lot of tasks to complete - like an email or brochure or ad campaign. The due dates from those sub-projects are cross-predecessor linked to the Master project - works like a charm
However, many of the assets are completed via Requests that don't get turned into projects. I have setup Request Queues within the master project so the Requests are all nicely lined up but I would be most happy if the due date of the request could be tied to the due date of the task in the Master project. Is there a way to do this, or is it but a dream I'm having?