I'm trying to pull hours & minutes between actual start and actual completion on an issue. I see a field for "Actual Hours", but it pulls all zeros. Is there a code to pull hours/minutes between start/end? I've tried
displayname=Act Time Taken
linkedname=direct
textmode=true
valueexpression=WORKHOURSDIFF({actualStartDate},{actualCompletionDate})
valueformat=HTML
also w/
valueexpression=WEEKDAYDIFF({actualStartDate},{actualCompletionDate})
Thanks,
Vin
Solved! Go to Solution.
Views
Replies
Total Likes
Thank you Richard! I think this will work. I noticed some issues returned 0 because the start/end time was outside working hours (since it can be a user globally).So going to see how to calculate those without capturing full 24 hours for other issues.
Views
Replies
Total Likes
Hi Vin,
Try WORKMINUTESDIFF instead, then divide by 60 to get the number of hours. The below textmode should do it
valueexpression=ROUND(DIV(WORKMINUTESDIFF({actualCompletionDate},{actualStartDate}),60),2)
Best Regards,
Rich.
Views
Replies
Total Likes
Thank you Richard! I think this will work. I noticed some issues returned 0 because the start/end time was outside working hours (since it can be a user globally).So going to see how to calculate those without capturing full 24 hours for other issues.
Views
Replies
Total Likes
No problem Vin. If this solved your problem, please mark it as a Correct Answer so that others know that the solution works.