0 Day Task Durations showing as "Late"
Hello,
Is there a way to prevent 0 Day task durations from showing as "Late?" We don't use planned hours and have our task constraints set to "As Soon as Possible." We were told a couple ways to do this which we don't really prefer:
1. Change task duration to 1 day and manually make the due on date the same day
2. Change the schedule mode on a project to "Completion Date"
I have tried adjusting our project schedule from the typical 9a-5a to 5a-midnight to see if that made any difference, but it did not.
Any help or other ideas would be appreciated!