Expand my Community achievements bar.

Wondering how Workfront Proof works? Join our AMA on May 8th and ask our Community experts!
SOLVED

Trigger for sprints

Avatar

Level 3

I want to move all remaining open projects when a sprint ends to the next sprint but I'm having confusion where to start.  What do I use as a starting trigger, as none of  them seems to work with sprints.  Any ideas where to start.  Sorry newbie to Fusion.  Thanks in advance.  

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Yeah exactly, and you should be able to do a search for the iteration (ITRN) where $$TODAY is between the start date and the end date of the iteration.

View solution in original post

4 Replies

Avatar

Community Advisor

Since it sounds like you're wanting to tie this to the end of a sprint, which is on a schedule, I would just setup your fusion scenario on the same type of schedule instead of using any type of automatic trigger.

Avatar

Level 3

@ChrisStephens thanks for your reply.  So maybe I'm over thinking it.  You are saying have the scenario use a search record module on a custom schedule on the days my sprints end and then use a update record to reassign the still open projects to the next sprint?  But how do I get t he current sprint?

Avatar

Correct answer by
Community Advisor

Yeah exactly, and you should be able to do a search for the iteration (ITRN) where $$TODAY is between the start date and the end date of the iteration.

Avatar

Administrator

Did you find the suggestions helpful? Please let us know if you need more information. If a response worked, kindly mark it as correct for posterity; alternatively, if you found a solution yourself, we’d appreciate it if you could share it with the community. Thank you! @FrankatMSC