Trigger for sprints

  • March 10, 2025
  • 1 reply
  • 561 views

I want to move all remaining open projects when a sprint ends to the next sprint but I'm having confusion where to start.  What do I use as a starting trigger, as none of  them seems to work with sprints.  Any ideas where to start.  Sorry newbie to Fusion.  Thanks in advance.  

Best answer by ChrisStephens

Yeah exactly, and you should be able to do a search for the iteration (ITRN) where $$TODAY is between the start date and the end date of the iteration.

1 reply

ChrisStephens
Community Advisor
Community Advisor
March 11, 2025

Since it sounds like you're wanting to tie this to the end of a sprint, which is on a schedule, I would just setup your fusion scenario on the same type of schedule instead of using any type of automatic trigger.

FrankatMSC
Level 4
March 12, 2025

@chrisstephens thanks for your reply.  So maybe I'm over thinking it.  You are saying have the scenario use a search record module on a custom schedule on the days my sprints end and then use a update record to reassign the still open projects to the next sprint?  But how do I get t he current sprint?

ChrisStephens
Community Advisor
ChrisStephensCommunity AdvisorAccepted solution
Community Advisor
March 13, 2025

Yeah exactly, and you should be able to do a search for the iteration (ITRN) where $$TODAY is between the start date and the end date of the iteration.