Cross Project Predecessors

Avatar

Level 10

Has anyone been able to read cross project predecessor information in Fusion?  We are trying to read the predecessor projected completion date to then reset the planned start date on the second project to have accurate capacity planning. 

 

Project A - Task 3 need to be completed  for Project B Task 1 to start. 


I'm not seeing where I can pull predecessor from a different project.  Only the predecessor information from that same project. 

KIMBERLYREA_0-1738089148935.png

KIMBERLYREA_1-1738089164214.png

 

2 Replies

Avatar

Community Advisor

Hi Kimberly.

 

Not sure what your module is that you are using in the  screenshot above but what I have done in the past is to use the "read related records" to get the predecessor collection details of a task. Then you can use a read record to get the task details of the predecessorID

 

KellieGardner_0-1738183190267.png

 




Avatar

Level 10

Thanks. I'll check that out and see what I can do.