  • Hi everyone, Thanks for the feedback! We have identified it as a bug and are working on the resolution. The reason for the behavior is because the link format changed to support New Workfront Experience but it shouldn't have affected Classic. Thanks, Vazgen Babayan Product Manager Workfront

    Type

    Questions

    Views

    1.1K

    Likes

    0

    Replies

    0
  • Hi Lauren, David This is actually working as designed since Resource Planner uses duration to calculate the hours per period information. We take the hour value and use the duration as a denominator and as a result skip 0 duration items. If the duration is anything greater than 0, the hours will app...

    Type

    Questions

    Views

    1.0K

    Likes

    0

    Replies

    0
  • Hi Jane, I just double checked and the survey is open to public, it can be that Google Forms are blocked by IT on your end. Vazgen Babayan Product Manager Workfront

    Type

    Questions

    Views

    513

    Likes

    0

    Replies

    0
  • Hi Skye, I tried to keep it vague intentionally not to keep reference to the existing tools as the questions are more about how work gets assigned out and less about the solution we have in place today. I do see how "the view" could have been misleading though. I will add some information on t...

    Type

    Questions

    Views

    513

    Likes

    0

    Replies

    0
  • You need to be a Planner user to see the People > Planning tab, but if the Planner User view was shared via the URL, it can be accessed by Workers and Reviewers via that URL. Vazgen Babayan Product Manager Workfront

    Type

    Questions

    Views

    976

    Likes

    0

    Replies

    0
  • Hi Anthony, Have you raised this with support already? The hours should show for the case you mentioned so it should be good for them to go through the troubleshooting process. @Colleen Masters since 19.2 Resource Manager access is no longer needed for Resource Planner. Ability to access the tool is...

    Type

    Questions

    Views

    976

    Likes

    0

    Replies

    0
  • Hi everyone, My name's Vazgen and I'm a Senior Product Manager at Workfront, over the Resource Management enhancements. One of the key ideas we are exploring right now is the ability to manage assignments in bulk and we had questions we'd love to get community feedback on. You can find those in the ...

    Type

    Questions

    Views

    513

    Likes

    0

    Replies

    5
  • Hi everyone,Thanks for all the feedback regarding this! The ability to report on Budgeted Hours have been introduced with 19.3 release. Please refer to the following article for more information: https://experience.workfront.com/s/article/Report-Budgeted-Hour-1228917083Please give the functionality ...

    Type

    Ideas

    Views

    794

    Likes

    0

    Replies

    0
  • Hi everyone, The changes have been reverted and the label "Subject" has returned. We will return to solving the confusion problem in the scope of a general initiative of enhancing Workfront intake solution. Thank you for taking time and providing feedback on the change! Thanks, Vazgen Babayan Produc...

    Type

    Questions

    Views

    683

    Likes

    0

    Replies

    0
  • Hi everyone, Thanks again for all the feedback! The goal of the change was to reduce confusion yet it appears that we introduced more of it. Thanks for your active participation and monitoring the situation with the end users as well. We will revert the change next week and I will continue investiga...