Expand my Community achievements bar.

Don’t miss the AEM Skill Exchange in SF on Nov 14—hear from industry leaders, learn best practices, and enhance your AEM strategy with practical tips.
SOLVED

sum help. Multiply cell b + c + d * 200000 / a

Avatar

Level 3

This formula is driving me crazy. Its a 3 step process. For one cell.

I need to add cell  b + c + d


Then take that number and times by 200,000


then take that number and divide by a

Does anyone have an idea?

1 Accepted Solution

Avatar

Correct answer by
Level 5

Hi,

Following radzmar instruction above to change the code to be

I have made the modifications and uploaded the file here https://acrobat.com/#d=gv3yzm73ZD-8gb-hPOlVbQ

Can you try that document and see if it works for you, this works for me, when

a != 0

b,c,d,e can be 0

Hope this helps

Malcolm

View solution in original post

30 Replies

Avatar

Level 3

I get zeros in TIR and LTA fields..

Im using Livecyle and testing in acrobat..


ss2.png

Avatar

Level 5

Hi Radzmar,

It doesn't work for me because I have the console set up to show when an exception is thrown and break so no more code runs, if I switch that off it is works without any visible problems, just as I noticed it I thought I should mention it.

Regards

Malcolm

Avatar

Level 3

Barlae are you able to see a total other than 0 in the TIR and LTA fields?? I cant, it worked yesterday and now i get 0s

Avatar

Level 10

Ahhh ok,

I thought all values have to be greater than 0.

If not, change the script into:

Avatar

Level 5

Hi,

This is what I get.

resultTAble.jpg

Which looks roughly like what I expect to see.

Regards

Malcolm

Avatar

Level 3

hi radzmar, let me give your script a spin..

Thank Your so very much for attempting to help me fix this mess

Avatar

Level 3

Crap, the calculations are still not working on my end for the TIR or LTA fields.

fields a - e are whole number 0 - 1000000

field f is b - e added up

TIR is field f x 200,000 / field a


LTS is field b - d added up, x 200,000 / field a

-----------------------------------------------------------------


Field A will never be zero

Field B could be zero
Field C could be zero, but not likely
Field D could be zero, but not likely
Field E could be zero
Field F could be zero

Avatar

Correct answer by
Level 5

Hi,

Following radzmar instruction above to change the code to be

I have made the modifications and uploaded the file here https://acrobat.com/#d=gv3yzm73ZD-8gb-hPOlVbQ

Can you try that document and see if it works for you, this works for me, when

a != 0

b,c,d,e can be 0

Hope this helps

Malcolm

Avatar

Level 3

Malcom, I dont know what the difference between your form and mine was. Probably something small and silly.

But it works!! It works great.....

Thank you so much

Radzmar, Thank you so much for helping me get this mess fixed

Now one little last question and i will be one happy camper... Is there a way to only show 2 decimal places?

Avatar

Level 3

Nevermind I figured that out too