Expand my Community achievements bar.

SOLVED

Another question regarding Dates

Avatar

Level 4

Hi, I have another question regarding the use of the date field in Adobe Designer 8.  I have the field set up so that either the person can enter the date, lets say, 12-12-11 and it will convert to December 12, 2011, or, the user can click on the calendar that is attached to the date field and make a date selection.  My question is this.  Is there a way that not only can the calendar go to any date by selecting < or >, but can also go to a specific year << or >>?  We have contracts that extend for 2 and 3 years and would like to have this option available.

Thanks for any help you can provide. 

Below is how I currently have my date fields set up.

In the Field section:

Display Pattern:  MMMM D, YYYY

Edit Pattern:  M-D-YY

Value section:

MMMM D, YYYY

Date must be entered as i.e., January 12, 2012

Binding section:

MMMM D, YYYY

1 Accepted Solution

Avatar

Correct answer by
Level 10

The calendar widget allows you to select other years.

When you open the calendar, click on the months name, the calendar will show you all months of the current year.

When you then click on the year, it shows you all years of the current decade...

Unbenannt.png

View solution in original post

2 Replies

Avatar

Correct answer by
Level 10

The calendar widget allows you to select other years.

When you open the calendar, click on the months name, the calendar will show you all months of the current year.

When you then click on the year, it shows you all years of the current decade...

Unbenannt.png

Avatar

Level 4

Thank you very much radzmar.  I did not know this.