Hi All,
Wondering if someone would be able to share some data/figures around large data transfer (assets) using content transfer tool from non-cloud env to cloud env?
Need this for migration planning and timeline estimation.
What were the sizes of transfer sets used? (Asset size or numbers)
How much time did it take to transfer that size/number of Assets?
Thanks in advance.
Solved! Go to Solution.
Views
Replies
Total Likes
@asn_india I found an article (non-Adobe) that might be of great help: https://implementationdetails.dev/blog/2021/08/05/ctt-extraction-deep-dive/
Hope this helps.
@asn_india As per this document https://experienceleague.adobe.com/docs/experience-manager-cloud-service/moving/cloud-migration/cont... you can create a maximum of 10 migration sets in order to initiate content transfer.
Since the help doc talks about blobs and data stores, I am assuming large data set should be allowed.
Haven't tried this feature personally, Adobe Daycare support might have a ball park estimate for you to get started.
@asn_india I found an article (non-Adobe) that might be of great help: https://implementationdetails.dev/blog/2021/08/05/ctt-extraction-deep-dive/
Hope this helps.