Hi Team,

 

I need to understand now below option works, not able to understand 2 different options, kindly help.

Try again later if outside of execution period

URL :- https://experienceleague.adobe.com/en/docs/campaign-classic/using/automating-with-workflows/flow-con... 

 

Regards

 

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi @random_guy_tech ,

Consider the below workflow,

ParthaSarathy_0-1711439679119.png

 

Time constraint activity settings:

ParthaSarathy_1-1711439731097.png

Case -1 : If 'Try again later if outside of execution period' is Unchecked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed and workflow will get finished. 

- If the workflow triggers at any time between 8 AM to 9 AM, then both JS-1 and JS-2 will get executed. 

 

Case - 2 : If 'Try again later if outside of execution period' is Checked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed at 7 AM  and the workflow will wait for the time specified in 'Time constraint' activity, and once the time is reached, then JS-2 will get executed at 8 AM.

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

Hi @random_guy_tech ,

Consider the below workflow,

ParthaSarathy_0-1711439679119.png

 

Time constraint activity settings:

ParthaSarathy_1-1711439731097.png

Case -1 : If 'Try again later if outside of execution period' is Unchecked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed and workflow will get finished. 

- If the workflow triggers at any time between 8 AM to 9 AM, then both JS-1 and JS-2 will get executed. 

 

Case - 2 : If 'Try again later if outside of execution period' is Checked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed at 7 AM  and the workflow will wait for the time specified in 'Time constraint' activity, and once the time is reached, then JS-2 will get executed at 8 AM.