Need understanding for Time Constraint

  • September 3, 2024
  • 1 reply
  • 672 views

Hi Team,

 

I need to understand now below option works, not able to understand 2 different options, kindly help.

Try again later if outside of execution period

URL :- https://experienceleague.adobe.com/en/docs/campaign-classic/using/automating-with-workflows/flow-control-activities/time-constraint 

 

Regards

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by ParthaSarathy

Hi @random_guy_tech ,

Consider the below workflow,

 

Time constraint activity settings:

Case -1 : If 'Try again later if outside of execution period' is Unchecked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed and workflow will get finished. 

- If the workflow triggers at any time between 8 AM to 9 AM, then both JS-1 and JS-2 will get executed. 

 

Case - 2 : If 'Try again later if outside of execution period' is Checked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed at 7 AM  and the workflow will wait for the time specified in 'Time constraint' activity, and once the time is reached, then JS-2 will get executed at 8 AM.

1 reply

ParthaSarathy
Community Advisor
ParthaSarathyCommunity AdvisorAccepted solution
Community Advisor
September 3, 2024

Hi @random_guy_tech ,

Consider the below workflow,

 

Time constraint activity settings:

Case -1 : If 'Try again later if outside of execution period' is Unchecked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed and workflow will get finished. 

- If the workflow triggers at any time between 8 AM to 9 AM, then both JS-1 and JS-2 will get executed. 

 

Case - 2 : If 'Try again later if outside of execution period' is Checked:

- If the workflow triggers at 7 AM (before 8AM or after 9 AM), only JS-1 will get executed at 7 AM  and the workflow will wait for the time specified in 'Time constraint' activity, and once the time is reached, then JS-2 will get executed at 8 AM.

~  ParthaSarathy S~  Click here to join ADOBE CAMPAIGN USER GROUP for Quarterly In-person | Hybrid | Virtual Meetups
Level 2
September 3, 2024

Thanks for help @parthasarathy