Workload Balancer Showing Zero Hours

Avatar

Level 1

I am having an issue where I have users assigned to tasks however their hours are showing zero. This changed when I updated the task assignments to be their job role names instead of their actual user name because I am working with 300+ projects and want to resource level. Any insight into why their hours might be showing zero if they're assigned to a task with hours? Also note that each of the project tasks are set to start and end during work hours. 

2 Replies

Avatar

Community Advisor

It sounds like you might be looking at the top section of Workfront Balancer, which is dedicated to Unassigned Work (that is, tasks not yet assigned to a specific user). Once a task has a specific user assigned, it will drop to the Assigned Work section below.

Avatar

Community Advisor

Sean,

This is a good resource link to bookmark, https://experienceleague.adobe.com/en/docs/workfront-learn/tutorials-workfront/manage-resources/reso... as its connected to a series of content Adobe created to help with the understanding, configuration, and set up of resource management.  It might offer some additional insights.