We don't have info about when and who inserted Actual Start Date on a task

Avatar

Level 1

When a task is set to In Progress, the assigned user can manually change the Actual Start Date on the task. However, this is not logged anywhere (that I am aware of). Can I turn on logging of the "Actual Start Date" change in the System Activity section, like it is the case with Planned Completion Date? E.g. "so-and-so changed the due date to <date>" is always logged in the updates of a task.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Yes. If you are an admin and have access from setup you determine which fields are tracked. 

 

KellieGardner_0-1716326035553.png

KellieGardner_1-1716326063505.png

 

 

https://experienceleague.adobe.com/en/docs/workfront/using/administration-and-setup/set-up-wf/system...




View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Yes. If you are an admin and have access from setup you determine which fields are tracked. 

 