Expand my Community achievements bar.

Interested in getting an Adobe Workfront certification? Don't miss our AMA on June 10th, where our experts will be available to answer any questions you may have about getting certified!
SOLVED

We don't have info about when and who inserted Actual Start Date on a task

Avatar

Level 1

When a task is set to In Progress, the assigned user can manually change the Actual Start Date on the task. However, this is not logged anywhere (that I am aware of). Can I turn on logging of the "Actual Start Date" change in the System Activity section, like it is the case with Planned Completion Date? E.g. "so-and-so changed the due date to <date>" is always logged in the updates of a task.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Yes. If you are an admin and have access from setup you determine which fields are tracked. 

 

KellieGardner_0-1716326035553.png

KellieGardner_1-1716326063505.png

 

 

https://experienceleague.adobe.com/en/docs/workfront/using/administration-and-setup/set-up-wf/system...




View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

Yes. If you are an admin and have access from setup you determine which fields are tracked. 

 

KellieGardner_0-1716326035553.png

KellieGardner_1-1716326063505.png

 

 

https://experienceleague.adobe.com/en/docs/workfront/using/administration-and-setup/set-up-wf/system...