View Cross-Project Predecessor Relationships on the Gantt Chart

Avatar

Level 8
Does anyone understand this update in 2018.2? I understand the concept, but I don't understand how to set predecessors between projects in order to view them on the gantt chart? I know how to set predecessors between tasks on a project. (we have these on all of our project templates) "https://support.workfront.com/hc/en-us/articles/360001978674?flash_digest=b8b4652b4b5dc0883d2cca021d155a5208295a1f#view-cross-project-predecessor-relationshipts-in-the-gantt">View Cross-Project Predecessor Relationships on the Gantt Chart in a List of Projects Thanks in advance to anyone who can help clarify this udate in the 2018.2 release! :) Sydney Peterson Diversified Communications, Inc.
3 Replies

Avatar

Level 1
Hey Sydney, Thanks for your comment. I think the article "https://support.workfront.com/hc/en-us/articles/216741968">Understanding Cross-Project Predecessors has the information you're looking for. I've updated the article "https://support.workfront.com/hc/en-us/articles/222389867?flash_digest=788d4c88f8fa997004ac12361c4efe65fbeafb65">Configuring How Information Is Displayed on the Gantt Chart with this information to help point users in the right direction in the future. Please let me know if you need anything else. Thanks, Courtney Christensen Technical Writer I Workfront

Avatar

Level 8
Thank you Courtney! I understand this now. :) Sydney Peterson Diversified Communications, Inc.

Avatar

Level 1
You're welcome! We love getting feedback from customers to improve our documentation. If you have any questions or suggestions in the future, feel free to leave a comment at the bottom of the article itself, and we'll make sure to get back to you. Thanks! Courtney Christensen Technical Writer I Workfront