Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!

Updating Default Revenue type?

Avatar

Level 2
Hi all - We have a regular issue that when we copy tasks from projects, the copied version defaults to "non billable" instead of "role hourly" that is on the original project/task. This has caused us to set up exception reports that we check every monday to make sure we're counting our revenue properly so everyone has accurate data, but it can have a BIG impact. Is there somewhere that you can change the default to either match the original task, or just make it role hourly? Thanks in advance for your ideas! Laura O'Malley Operations Manager precisioneffect Boston, MA
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 2

Hi Laura! - When copying Tasks to other Projects, the original data should be copied over as well. If you select 'Clear Financial Data' when copying over the Task, that will change the Revenue Type to 'Not Billable'.

You can change your preferences in Setup > Project Preferences > Tasks & Issues. There you can set the default Revenue Type upon Task creation. Depending on how your Tasks are being created and copied, this could affect it.

Below are some articles that could help explain this a little better, however intended behavior of copying Tasks is to carry over all properties of those Tasks. If that's not the behavior you're experiencing, I would suggest creating a case for our Support Team to look further into if you haven't already.

https://one.workfront.com/s/article/Copy-and-Duplicate-Tasks-218695605

https://one.workfront.com/s/article/Tasks-and-Issues-Preferences-189854638?language=en_US&r=218&ui-f...