Hi everyone -
I'm hoping someone can help me understand task tracking mode. I'm running a pilot where we're looking to revamp some projects to include "catch-all" tasks. They will not be resolved after finishing one task, but used for multiple needs over the course of a month, to be resolved at month's end.
I'm changing some of the task's modes from "user must update" to "auto-complete." From what I understand, the tasks should complete at due date except if it has a predecessor which is incomplete. The tasks I'm using have no predecessors and a due date of last business day of month/ 5:00p.m. For some reason, I cannot get tasks to auto close no matter what I do.
Is there something I'm missing?
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
at least one thing to check is project update type, as per documentation:
also auto-complete happens "daily" at best, not at the very moment when the due date is.
good luck!
at least one thing to check is project update type, as per documentation:
also auto-complete happens "daily" at best, not at the very moment when the due date is.
good luck!
Ahh, thank you!