Hi. I am trying to help a user set up a template and I am not sure how to accomplish what they need.
Schedule Mode = Completion Date
All tasks will work backwards from set Completion Date. They would like to be able to set the Task Start Dates on the template to be X number of days from Completion Date. So Task 1 needs to start 4 weeks prior to Completion Date, Task 2 needs to start 3 weeks from Completion Date, Task 3 needs to start 5 days prior to Completion Date etc...
Do I need to enter a formula to make this work? Is there a simple solution I am overlooking? Thank you!