Task Update on a View

Avatar

Level 2

Can someone please tell me how to show the latest Task Update in a view? 

Thanks, Cathie

1 Accepted Solution

Avatar

Correct answer by
Employee

Do you mean the text from the last update made on the task? Try Last Note > Note Text

View solution in original post

2 Replies

Avatar

Correct answer by
Employee

Do you mean the text from the last update made on the task? Try Last Note > Note Text

Avatar

Community Advisor

@allisonlWF is correct, adding a column for Last Note > Note Text will show the latest Update in that task.