If I assigned a Use to a template, will that User be notified of the task?

I don't want them the template to show in the to-do list unless it was attached to a project. 

 

Thank you,

Jenny

1 Accepted Solution

Avatar

Correct answer by
Level 5

Hi Jenny, no a template task assignment will not show up on their My Work / My Tasks area of Workfront

View solution in original post

2 Replies

Avatar

Correct answer by
Level 5

Hi Jenny, no a template task assignment will not show up on their My Work / My Tasks area of Workfront

Avatar

Level 3

Thank you very much!