Expand my Community achievements bar.

SOLVED

Task report with chart of task completed prior to the completion date compared to past the completion date

Avatar

Level 3

Any ideas on how to set up a simple report using a chart option of either the number or percentage of tasks completed by the planned completion date compared to those completed after the planned completion date.  I can't seem to set the report up correctly to get the data I want on a chart.  Thanks!

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

 

Hi @SuzyF,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug

 

TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use

View solution in original post

1 Reply

Avatar

Correct answer by
Community Advisor

 

Hi @SuzyF,

 

I suggest you group by Task Progress (e.g. On Time, At Risk, Behind, Late), then chart as you see fit (e.g. Pie Chart, Stacked Column over time, etc.) .

 

Regards,

Doug

 

TIP: if this solved your problem, I invite you to consider marking it as a Correct Answer to help others who might also find it of use