Leiste mit Community-Erfolgen erweitern.

Don’t miss the Workfront AMA: System Smarts & Strategic Starts! Ask your questions about keeping Workfront running smoothly, planning enhancements, reporting, or adoption, and get practical insights from Adobe experts.
GELÖST

Task Report - Tasks Ready to Start

Avatar

Level 4


Greetings!

 

I'm looking to include in my report the following:

  1. Tasks assigned to $$USER.ID
  2. Predecessor Is Complete - True
  3. Project Status - In Progress
  4. Task Percent Complete - Not Equal to 100%
  5. Task is Not equal to Complete, Canceled or On Hold
  6. Tasks with no predecessors - How do I include this one in my report? I'm not figuring this one out. 

Thank You, Deb

Themen

Anhand von Themen werden Community-Inhalte kategorisiert und Sie können so relevanten Inhalt besser finden.

1 Akzeptierte Lösung

Avatar

Korrekte Antwort von
Community Advisor

Hi Deb -

 

You'll want to use the filter "can start" = True. This will pull in anything that is ready to start - meaning it has predecessors complete or does not have an dependencies.

 

KellieGardner_0-1710946586653.png

 




Lösung in ursprünglichem Beitrag anzeigen

3 Antworten

Avatar

Community Advisor

In order to make things consistent and simple we have our users utilizing the new home and specifically the My Tasks widget, I am just curious if you have tried using this tool and how it might have potentially fallen short of your needs.

Avatar

Korrekte Antwort von
Community Advisor

Hi Deb -

 

You'll want to use the filter "can start" = True. This will pull in anything that is ready to start - meaning it has predecessors complete or does not have an dependencies.

 

KellieGardner_0-1710946586653.png

 




Avatar

Level 4

Perfect. Many thanks!