Task - Percent Complete Aggregation in a Report

Avatar

Level 4

Hey Community,

Real quick... How can I get an aggregated number of %Complete for multiple tasks in a task report without using the Task Duration and Task Planned Hours information? I have as an input only Task Percent Complete values. Need to get the Overall/Average %Complete among multiple tasks in a given grouping (see the attached screenshot). Thank you in advance.

Thanks,

+Pavlin

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 4

I guess, that was an easy one. Shortly after I posted my question, I got the answer myself. Thanks.

View solution in original post

2 Replies

Avatar

Correct answer by
Level 4

I guess, that was an easy one. Shortly after I posted my question, I got the answer myself. Thanks.

Avatar

Employee

I am so glad you shared this thinking! If you had the question, you know someone else would as well!