Splitting time allocation

Avatar

Level 1
Can you please help me. I would like to split a task for Project Management over 10 weeks a 4 hours per week. can this be done without creating a task for each week? Cheers Phil Phil Cullen Adaptiv Integration
3 Replies

Avatar

Level 10
What I do is create one Task called "Miscellaneous Project Management Activities" with a Duration of 10 weeks, and a Planned Hours of 40 hours and it should spread it out for you.

Avatar

Level 1
Thank you Vic , that worked perfectly. Philip Cullen Adaptiv