Currently our users can directly change a start or end date in a project, which changes the associated task constraint to Must Start On or Must Finish On. I have memory of users not being able to do that previously; the only way to change a date was through adjusting the duration.
Is there a setting that allows a Planner to edit task start/end dates only through duration? If so, where can that be accessed?
If you have a recommendation on the best practice for date adjustment for users new to project management/Workfront, please let me know.
Thanks!
Topics help categorize Community content and increase your ability to discover relevant content.
If they have manage access you can't limit their ability to move the dates.
Options
valueexpression={plannedStartDate}
querysort=plannedStartDate
valueformat=atDate
displayname=
linkedname=direct
namekey=plannedStartDate
It's really going to be a coaching exercise with your users. Explaining to them that hand picking a date overrides the functionality of Workfront's timeline features.
Hi Kellie. Thanks for the answer.
Has it always been like this? I could have sworn that our users weren't able to hard code dates when the constraint was set to As Soon As Possible and were only able to change dates by adjusting the duration.
Views
Replies
Total Likes
in a sense you are both right @HannahKr2 @KellieGWAB
when task is set to ASAP, planned dates are greyed out and not editable, while duration is still editable.
At the same time, depending on user's task level access they can still go in, adjust the constraint and edit the dates...
Views
Replies
Total Likes
You are right it does gray them out in the task settings area however from the main project screen where most planners setup their timelines and do their planning, it does not.
All dates are editable and the only way around it is to control it from their view.
Views
Replies
Total Likes
Hi Kellie. Thanks for the answer.
Has it always been like this? I could have sworn that our users weren't able to hard code dates when the constraint was set to As Soon As Possible and were only able to change dates by adjusting the duration. One of the biggest pieces of feedback we received was "Dates can't be changed" so this is throwing me for a loop now that they can be changed with a double click.