Hello! My agency uses a high level milestone task schedule with 5 phases. Because of this, when we utilize the People - Working On view we are not getting accurate hours on a daily or weekly basis as the system divides up the assigned hours over the time span of the milestone task. Is there a way to front load or back load time for certain resources within a task? IE If Jon is scheduled to work 15 hours over 15 days on the concepting phase, can I set WF so that that 10 of the hours are done within the first 5 days instead of the system showing he is working 1 hour per day on this task? Thanks! Amanda Amanda Levine Liberty Mutual Insurance Company