Reporting - All notes/updates

Avatar

Level 3
Reporting - All notes How do you pull multiple task updates for a given timeframe (example last week)? Currently it is only showing the last update when there have actually been 3 updates for that task within the week. We want the report to show all the updates for that task. Example: Joe added a task update on 4/1 Brian added a task update on 4/2 Debbie added a task update on 4/3 We would like all there of these updates to show on the report. Currently it will only pull Debbie’s since she is the last to update.
1 Reply

Avatar

Level 4
You need to create a note report not a task report then add the appropriate groupings and filters.