Hi WF Community,
Does anyone know if it's possible to filer a report (e.g. task report) based on tasks that have cross-project predecessors?
Can't seem to find an appropriate field within a task report for cross-project dependencies.
Thanks.
Nick
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Try this (updated after posting)
predecessorsMM:name_Mod=notblank
predecessorsMM:projectID=FIELD:projectID
predecessorsMM:projectID_Mod=ne
Views
Replies
Total Likes
Try this (updated after posting)
predecessorsMM:name_Mod=notblank
predecessorsMM:projectID=FIELD:projectID
predecessorsMM:projectID_Mod=ne
Views
Replies
Total Likes
That worked. Thanks, Adina!