Report to identify cross-project dependencies

Avatar

Level 10

Hi WF Community,

Does anyone know if it's possible to filer a report (e.g. task report) based on tasks that have cross-project predecessors?

Can't seem to find an appropriate field within a task report for cross-project dependencies.

Thanks.

Nick

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Level 8

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

View solution in original post

2 Replies

Avatar

Correct answer by
Level 8

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

Avatar

Level 10

That worked. Thanks, Adina!