Hi WF Community,

Does anyone know if it's possible to filer a report (e.g. task report) based on tasks that have cross-project predecessors?

Can't seem to find an appropriate field within a task report for cross-project dependencies.

Thanks.

Nick

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by AdinaPi1

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

2 replies

AdinaPi1Accepted solution
Level 9
September 24, 2020

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

NickVa7Author
Level 9
September 25, 2020

That worked. Thanks, Adina!