I am looking for a way to report on Planned Hours by Role by Project. Essentially, looking for a way to report on the Role Allocation on the projects. We were able to create task level reports that have the planned totals by task which we can manually roll up in excel, or even located the information in an assignment report however was not able to figure out how to roll up the totals and provide like 1 row by project.
해결되었습니다! 솔루션으로 이동.
토픽은 커뮤니티 콘텐츠를 분류하여 관련성 있는 콘텐츠를 찾는 데 도움이 됩니다.
조회 수
답글
좋아요 수
If you add a grouping for the Job Role Name then you can sum the Planned Hours column. Then have the report load to the Summary Tab by default under the report options. This will display one line item for each role that is totaled up for planned hours.
Grouping:
Planned Hours Summed:
Report Output:
If you add another grouping and have the Project Name be the 1st grouping, you can group them by the projects you want to pull in with the roles underneath.
Double grouping:
If you add a grouping for the Job Role Name then you can sum the Planned Hours column. Then have the report load to the Summary Tab by default under the report options. This will display one line item for each role that is totaled up for planned hours.
Grouping:
Planned Hours Summed:
Report Output:
If you add another grouping and have the Project Name be the 1st grouping, you can group them by the projects you want to pull in with the roles underneath.
Double grouping:
This is the way!
조회 수
답글
좋아요 수
Thank you, this helps a lot.
조회 수
답글
좋아요 수
You're welcome!
조회 수
답글
좋아요 수
Great stuff @KierstenKollins -- thanks for sharing!
Having reached the edge of what's possible within Workfront natively using Kiersten's technique, @MichaelSMN, if you are interested in doing similar but:
I invite you to consider our AFA Burn Report solution, and would be happy to chat further via doug.denhoed@atappstore.com
Regards,
Doug