Can someone assist with what the the reporting filters/text mode (or calculated field if needed) would be to create a report of all active projects in which the planned completion date is greater than 6 months?
Thanks in advance!
Laura
Solved! Go to Solution.
Aha. This may be more helpful as a FILTER in your Projects page instead of a report...
If you have your settings as the start date = the day you're creating the project, you could have the filter be project due on (planned completion date) is less than TODAY+6months
Thoughts?
You're in luck, this is very simple! Include whatever date appropriate, this is example:
If you found this helpful, please mark correct to help others : )
Views
Replies
Total Likes
Thank you Madalyn.
However, what I am looking for is a filter that can be applied to all of our active projects. So the report will show all active projects in which the planned completion date is 6 months greater than the actual start date of the project.
Views
Replies
Total Likes
Aha. This may be more helpful as a FILTER in your Projects page instead of a report...
If you have your settings as the start date = the day you're creating the project, you could have the filter be project due on (planned completion date) is less than TODAY+6months
Thoughts?
Views
Likes
Replies
Views
Likes
Replies
Views
Likes
Replies