Question
"Work On It" Button & Actual Start/ In Progress
Hoping someone can help! I've searched high and low scouring the support area for the answer and still no straight forward yes or no on my question. Question: What EXACTLY does clicking "Work On It" affect? The expectation is that it would change the task's status to "In Progress" and set the actual start date to that moment in time when the user clicks "Work On It" Users in my organization are not finding this to be true. Which is an issue because we have predecessors using the Start-Start relationship and thus are not triggered unless the users are manually changing the progress rather than clicking "Work On It". Is anyone else experiencing this? What is the actual purpose of the button? I'm finding it hard to get buy-in from users to click "Work On It" AND update the percent complete to something partial to get the Status triggered to "In Progress"...they're barely using the Home/My Work views. Any suggestions? Thank you in advance :)