Project Owner Name as Calculated Field

Avatar

Level 2
Drawing a blank here! I assumed this would be easy, but nothing I am doing is working! I am trying to create a calculated field of Project Owner Name. To pull the Owner name into the custom form for some API work I am doing. I have tried the calculation as: Project: Owner: name AND Owner :Name , along with a few others. Any thoughts? Jessi Volaric
2 Replies

Avatar

Level 6
Are you making a Calculated Field on a custom form, on the project? If so, try "Owner.Name" with a period instead of a semi-colon. If you're wanting the calculated field on the custom form on the task in the project, try Project.Owner.Name Vincent Goodwin The Capital Group Companies

Avatar

Level 2
Ah, that was it. I knew I was close. Thanks! Jessi Volaric