Predecessor Articulation - First Week of the Upcoming Month

Avatar

Level 4

My paid media team asked me an interesting question I wasn't sure how to answer. Can we set a reporting Task due the day of the first week of the Upcoming Month? If so, any suggestions? Thank You!

トピック

トピックはコミュニティのコンテンツの分類に役立ち、関連コンテンツを発見する可能性を広げます。

1 返信

Avatar

Community Advisor

Check out this article on lags/predecessors for help. Month isn't indicated in here but it could maybe work with 'm' instead of 'w' for weeks, or you could use a predecessor for 4 weeks. For example, if you want a task due the first Monday in 4 weeks after task 5, I think it would be 5fs+42w (42 is 4=4wks and 2=the # assigned to Monday in lags). 

If this helped you, please mark correct to help others : )