Parent Task Issues and impact on Resource Planner

Avatar

Level 6
Hi I just wanted to highlight an issue we have encountered where some of our users have "inadvertently" made standalone tasks into parent tasks after they have added assignments, planned and actual hours to them. The hours for the original standalone task disappear from the project view and the original percentage complete reverts to zero. The hours are also effected in the Resource Planner. It can take a while to unpick, ensuring any changes feed through to the Resource Planner. The key message here is to advise your users not to convert standalone tasks into parents once actual hours have been logged. Happy Friday :-) All the best Jane Jane Bradshaw BAKKAVOR LTD