Hi Jim,
I've created the attached report. This has a similar style to your powerpoint report.
To create one like this, you create a project report, then use conditional formatting on each field to display different coloured circles depending on the content of the field. This can be used well for things like Project Status, Condition etc. Regarding the Issues column, I have only been able to do it based on the number of Open issues (e.g. over 5 is red, over 3 is orange etc).
Hope this helps.