Frank, We have the same problem with my company. I agree that it would be very helpful to be able to add milestones to multiple tasks. In our timelines, several different pieces make up a 'phase'. The workaround we are using is to break the timeline into parent tasks and duplicate each piece as a sub task. If you put the Milestone on the parent, it shows complete when the sub tasks are finished. Anthony, I considered a similar solution to the one you are using, but it doesn't allow you to take advantage of the Milestone views provided by Workfront. Have you found a solution to that? Or are you using custom reports to track your Milestones? Justin Cross