Hello,
I don't seem to find Best Practices for Cards. Our Teams rely heavily on the use of Kanban Cards that continuos to impact the Project Timeline negatively and keeps the Project Owners out of the loop.
As Best Practice, we advise the Project Team members are told to suggest a "Commit Date" when assigned to a Task in a Project. In this way the Project Owner gets a notification to accept (timeline gets automatically updated) or reject (Project Owner takes mediating actions). However, "Commit Date" does not seem to be an editable field in the Cards.
As an alternative, I was looking at having the assignee edit the Task Duration in the Card (and notifying the Project Owner). However, this Task Duration field does not seem to be available in Cards.
What would be the best practice for Team Members to work in the Kanban Cards while communicating with the Project Owner and not affecting the Project Timeline with undesired Constraint changes?