


We're looking at tying multiple projects to 1 parent project and would like to automate the completion of tasks on the parent project. For example:
Project A is the Parent Project with Tasks 1, 2 and 3. The Tasks are equal to Project B, C and D. If Project B is completed, is there a way to connect the predecessors or projects for Task 1 on Project A to be completed automatically?
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Sign in to like this content
Total Likes
Hi Lila,
I suspect the closest you could get would be to create a Task report that (using Handoff Date, Predecessors, and EXISTS) would present "Task 1 on Project A" to the viewer (ideally, along-side the now-complete "Last Task on Project B") so that the user could then easily manually mark it as complete (with the same Last Task on Project B Actual Completion Date, for consistency).
If that's too much work (or happens too frequently), you could automate it using Fusion or our UberCalc solution.
Regards,
Doug
Views
Replies
Sign in to like this content
Total Likes