Is there a way to change all the dates for tasks in an Agile project to the end date and not the start date of the project?

Avatar

Level 2

When creating an Agile project, the tasks default to the start date of the project. I would like to set the tasks and any consecutive tasks to take on the end date of the project or 1st sprint of the project.

Tópicos

Os tópicos ajudam a categorizar o conteúdo da comunidade e aumentam sua capacidade de descobrir conteúdo relevante.

1 Resposta

Avatar

Level 1

The closest you could get to this would be to change Schedule Mode for the Project to be based on Completion Date, or just bulk edit the tasks and change Task Constraint to Must Finish On and manually set the date.