Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Is there a way for an issue report to show if an issue is late, on time, etc. (tasks have "progress status", projects have "condition", but issues don't)?

Avatar

Level 1

Is there a way for an issue report to show if an issue is late, on time, etc.?  Meaning, if I am looking at the report today and the planned completion date for the issue was yesterday, can there be a column that shows the issue is "late"?  I don't see a "progress status" field option for issues like I see for tasks.  And projects have a "condition" field option that is equivalent to that.  When I choose "condition" for issues, all I get is "going smoothly, concerns, etc." which is tied to the last update.

 

Does anyone have a workaround that can maybe calculate the issue's progress status/condition (i.e. late, at risk, on time), depending on planned completion date and when the report is seen/run?

 

Any insight and/or help is greatly appreciated.  Thanks!

2 Replies

Avatar

Community Advisor

Hi @GiselleSeoane! What about an Issue Report with a column that uses custom text? To set it up, you could choose Planned Completion Date as the column, then Advanced Options > Add a Rule for this Column and then choose a date range for each set of criteria and enter the custom text / formatting (screenshot below). You could do $$TODAY for Late, $$TODAY+2d for At Risk, etc. (2d standing for days).

 

Hope this helps!Screenshot 2023-06-19 141349.png

 

Avatar

Level 1

Thanks so much for this!!!!  Although it's not perfect to calculate "behind", since status (and % comp) would help determine that, it's still a HUGE win to be able to export the report with issues identified as "late" and "on target".  I can just manually change some of the "on target" to "behind" depending on their status and % comp.

 

It's too bad we can't create a rule that has more that one truth like:

  • planned start date is < than today; and
  • status is = new

Thanks again!