Looking to see he dates/times of the status changes of a project - is there anyway to report on something like that or atleast see the path the status went on if not the dates/times?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Are you looking for something like this? 

Status History
Complete: 11/2/23 15:24 | Active: 8/3/23 9:12 | Ready to Assign: 7/31/23 10:39 | Planning: 3/13/23 16:00 |

 
If so, you can use the process outlined in Targeted Auditing Proof Of Concept by @Doug_Den_Hoed__AtAppStore. It was a little tricky to set up, but once it's done, it provides an easy way to see the status changes. Doug's a genius!
 

View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

Are you looking for something like this? 

Status History
Complete: 11/2/23 15:24 | Active: 8/3/23 9:12 | Ready to Assign: 7/31/23 10:39 | Planning: 3/13/23 16:00 |

 
If so, you can use the process outlined in Targeted Auditing Proof Of Concept by @Doug_Den_Hoed__AtAppStore. It was a little tricky to set up, but once it's done, it provides an easy way to see the status changes. Doug's a genius!
 