Is it possible to display Parent task and Child Task both in Calendar?

Avatar

Level 10

Hi

Is it possible to display Parent task and Child Task both in Calendar?

Mvh

Kundan

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 8

The only way I've found to do this is to create a separate item in the calendar that displays the parent tasks instead of the child using this selection menu.

Our calendars are either built around one person, one team, or one project. The project ones tend to look like this:

They're all the same project, but different elements.

However, if this isn't what you're looking for there is the custom option under the task labels options I screenshot above. I'm not familiar with how to really mess with that and would love any additional insight anyone has!

Avatar

Level 10

Thanks for the tips @Samantha Isin‚

Yesterday found one more recommendation in this regard, we can add {name}{parent:name} in custom area. Then it shows parent task and child task together.