I've included planned hours in template tasks but when I convert template to a project and change the assignment from role based (designer) to actual person (joe smith) planned hours go to 0. How can I keep planned hours?

Avatar

Level 2
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 10

Hi @Michelle Covello‚

This is not happening in our case, could you check "Duration Type" and "Task Constraints".