Hi Community,
I’m trying to filter out users without planned hours or who has worked on the project in past, but the user is no longer on the project as shown in screenshot below, unfortunately this filter does not seems to be working. Any idea on how to get this work so that I can only see users with active planned hours?
seeing users who have worked on the project in past and they are no longer in the project showing up in the view is very annoying to users,
Thank for your input and help.
Views
Replies
Total Likes
You should be able to hit the add filter option and type in planned hours. Then set it to greater than 0.
Views
Replies
Total Likes
thanks @KellieGWAB for your input. I did that, unfortunately, is not filtering correctly and is still pulling resources who are not on the project with zero planned hours - please screenshot below.
Views
Replies
Total Likes
I believe this is similar to running a report in resource planner. While the users don't have hours within the time frame you are viewing (June) at some point they did or will have hours on the project. Is there planned hours showing in your "overall" section of the report?
Views
Replies
Total Likes
Thanks again @KellieGWAB . The resources don't have planned hours at all on the project, in short they are not assigned to any task on the project. They worked on the project in the past, that is why Workfront is showing the history. Now is zero planned hours for the entire duration of the project as shown in screenshot.
Views
Replies
Total Likes
On every project I've tested this on in my instance it filters out all instances where planned hours equal to zero except when the user has logged actual hours.
I couldn't find any that exactly explains it in the documentation but the general concept of the report is that it allows you to view the progress, cost, or revenue of a project, program, or portfolio in a single report. You can also compare revenue against cost. My assumption would be that because it's comparing cost and there are actual hours that contribute towards the projects actuals it's not filtering them out.
Views
Replies
Total Likes
Good morning @KellieGWAB for your help again. If I understand you correctly are you referring the overall actual hours that the person have logged to the project in the past? (see screenshot below).
Is there any other method to filter them out when they are no longer on the project with zero planned hours?
Views
Replies
Total Likes
I did some testing and I think if you filter for the planned completion date to be within the date range you are looking at in the utilization report, it will filter them out of the report.
Views
Replies
Total Likes
Views
Likes
Replies
Views
Likes
Replies