I have a template that maps a project 9 months out. Often times, we end up not kicking off a project until 5 months out.
When this happens, I go in and manually adjust the timeline so that the durations are evenly reduced and distributed. Is there a way that the template can automatically do this?
Right now the template is set up as a "start from" but I have a fixed deadline that all my tasks work back from. So, if I use my 9 month template but my timeframe is only 5 months, it just has the first third of my tasks all overlapping and due at the same time.
Thanks in advance!