The reason I ask is because I am trying to create a visual report that will show the pacing of each milestone with in a project, but each project needs to be grouped within its portfolio. Just to be clear, the team isn't thrilled by the milestone report because they want to be able to see the duration/span of each milestone so they can better understand the pacing for the portfolio. I have attached a screenshot of the report i am constructing. Thanks for the help in advance!
Solved! Go to Solution.
Topics help categorize Community content and increase your ability to discover relevant content.
Try this:
textmode=true
group.0.valuefield=project:portfolio:name
group.0.valueformat=HTML
group.0.name=Portfolio
Try this:
textmode=true
group.0.valuefield=project:portfolio:name
group.0.valueformat=HTML
group.0.name=Portfolio
👏👏👏👏👏 Thank you @Adina Pierce‚ ! This made my Friday!