I am trying to use Baselines - but I am not seeing how I would show that a project has slipped a month from its start. Does anyone have a process they are using to calculate slippage in a project or a series of projects? Thanks in advance for any guidance you can provide!
Sue
Solved! Go to Solution.
Views
Replies
Total Likes
One way is to "save" initial planned dates as "set-once" calculated fields, and then show slippage in a second calculated field.
IF(ISBLANK({DE:myOrigPlannedCompletion})&&{status}="CUR", {plannedCompletionDate}, {DE:myOrigPlannedCompletion})
The above will set the field ONLY if it's still empty, and the status is CUR.
You can then create a second calc field to show the DATEDIFF
One way is to "save" initial planned dates as "set-once" calculated fields, and then show slippage in a second calculated field.
IF(ISBLANK({DE:myOrigPlannedCompletion})&&{status}="CUR", {plannedCompletionDate}, {DE:myOrigPlannedCompletion})
The above will set the field ONLY if it's still empty, and the status is CUR.
You can then create a second calc field to show the DATEDIFF
@SuzannaHathaway Just checking in — were you able to resolve your issue? We’d love to hear how things worked out. If the suggestions above helped, marking a response as correct can guide others with similar questions. And if you found another solution, feel free to share it — your insights could really benefit the community. Thanks again for being part of the conversation!